Activities performed
MULTIDISCIPLINARY project: BoP, plant, mechanical, civil, electrical and
automation detail design (BIM of modeling and management). Building and
structural construction management Civil and piping field engineering. Follow
up of technical documentation from suppliers.
Period of performance
2021 – 2023 Design phase
2022 – 2024 Construction phase
Project description
Plant covers a total area of 449,451 m2, of which about 71,000 m2 consist of
buildings. The project involves the installation of a combined cycle (CCGT) of
maximum size 860 MWe, replacing the existing carbon groups.
The project is an integral part of the programmatic actions planned in accordance
with the Integrated National Energy and Climate Plan for which the
conversion to gas or the decommissioning of coal-fired power plants is necessary.